Construction of pedestrian bridges at Juvisy-Sur-Orge station for the GPI

construction of 3 pedestrian bridges in Essonne

Construction of pedestrian bridges at Juvisy-Sur-Orge station for the GPI

As part of the future Intermodal Grand Pole (GPI) of Juvisy-sur-Orge in Essonne, Matière® is currently building the metal structure of pedestrian bridges.

 

construction of pedestrian bridges for the GPI

 

 

This project consists of 3 bridges manufactured by the Charmes factory (Condorcet, Seine and Mairie) and will be used for soft traffic such as bicycles or pedestrians.

 

Renovation works in the 7th largest railway station in France should facilitate connections between lines C and D, the bus stations, the future tramway but also improve the daily lives of users by opening neighborhoods.

 

Indeed, at the moment the GPI sees daily more than 1000 trains, 1300 buses, 104 000 travelers. It was therefore essential to rethink the GPI in order to offer an optimal mobility solution for the south of Paris and all its passengers.

 

 

The commissioning of the Intermodal Grand Pole (GPI) of Juvisy-sur-Orge is planned for 2020. Pending the completion of the works, everything is organized to minimize disruption.

 

 

 

 

The characteristics of the Seine footbridge:

  • Length: 80.47 m;
  • Width: 6.65 m;
  • Total weight: 136 t.

 

The characteristics of the City Hall footbridge:

  • Length: 73 m;
  • Width: 6.65 m;
  • Total weight: 120 t.

 

The characteristics of the Condorcet footbridge:

  • Length: 24 m;
  • Width: 3.2 m;
  • Total weight: 38 t including 15 t for the staircase.

 

 

 

 

Partager cet article :