Reunion: Update on the progress of the construction site of La Rivière Des Galets

construction site of La Riviere Des Galets

Reunion: Update on the progress of the construction site of La Rivière Des Galets

Back on the Matière® site, at the Riviere des Galets on the island of Reunion.

The construction of the 430-meter-long bridge continues, after more than two years of work.

 

Currently, the steel structure of the upstream deck is in place on its supports.

The part of the construction site concerning the Civil Engineering is in progress with the laying of the slabs and slabs of the work.

 

At the downstream deck, the metal frame is being assembled. For the moment, three out of four phases of the launching are done, the last phase of the launching should be carried out at the end of November / beginning of December 2019.

 

Reunionese are fully involved in this project which will streamline road traffic on this busy axis of the island, but also replace a former metal structure, more resistant enough to cope with weather events in the region.

 

To know more about this work and the details of the work undertaken, find all the details of the site of the river of pebbles in our previous article: the bridge of the Riviere des Galets